Maire Street & Tuatoru Street shared path upgrade work

Hutt City logo

Work is beginning on the Maire Street and Tuatoru Street car parking areas to incorporate shared path improvements.

A Council contractor has asked us to advise residents about work at the Community Centre car park, Corner of Tuatoru Street and Marine Parade.
DATES: Between Wednesday 1 March and Wednesday 22 March
Working hours: Monday to Friday Normal work hours, 7am to 6pm
Note: Road marking will occur during night-time hours on 2 March from 7:00 PM to 5:30 AM. (Weather/site condition dependent).
WHAT’S BEING DONE: Bollards removal, new removable bollards and signage installation, existing Line Removal, line marking, relocation of community sign board, wheels stop installation of carpark.
PARKING: To complete this work we need the parks highlighted red in the picture shown to be clear of vehicles and other obstructions between the above dates and times. Vehicles in the loading zone will be towed to the nearest suitable park available. If your vehicle has been moved, please check nearby streets before contacting Company
WEATHER: If works are not carried out on this date due to unsuitable weather or unforeseen circumstances, it will commence the next suitable day.
QUESTIONS: If you have any questions regarding this work, please contact Andrew Liu, Project manager, Expeditious Construction, 021 952 588

A Council contractor has asked us to let residents know about work in Maire Street:
WHERE: Maire Street Carpark at the corner of Maire Street & Karamu Street
DATES: Date Start 1st March 2023 Date End 16th March 2023
WORKING HOURS: Monday to Friday, 7am to 6pm
Attention: Road marking will occur during night-time hours on March 1st, from 7:00 PM to 5:30 AM. (Weather/site condition dependent).

WHAT’S BEING DONE: Line Marking, Traffic separator with concrete infill installation, Bollards removal

PARKING: To complete this work we need the parks highlighted red in the picture shown on reverse to be clear of vehicles and other obstruction between the above dates and times. Vehicles in the loading zone will be towed to the nearest suitable park available. If your vehicle has been moved, please check nearby streets before contacting Company
WEATHER: If works are not carried out on this date due to unsuitable weather or unforeseen circumstances, it will commence the next suitable day.
If you have any questions regarding this work, please contact:
Contact Name: Andrew Liu
Contact Title: Project manager
Contact Company: Expeditious Construction
Contact Number: 021 952 588